mediumScheduling
1. A corrective maintenance order requires an urgent spare part not in stock, and the scheduling parameters must reflect the material availability date rather than the originally planned start date. How does the system handle this rescheduling?
When a reservation or PR/PO is created for the operation and the material isn't available, the order's basic start date can be automatically or manually rescheduled based on the material availability date using the scheduling function (CO02/IW32 with 'schedule' or availability check). Availability control (checking rule) flags the shortfall, and if configured, the order scheduling type adjusts basic dates forward to match expected delivery, though this requires manual triggering of rescheduling in most standard corrective order scenarios since urgent orders often bypass automatic MRP-driven date shifts.